Projects:2016:New Hackerspace
Jump to navigation
Jump to search
Project
The Pixelbar Hackerspace will have to move to a new location, This location will be bigger than the current one ( +- 15m2 vs 75m2 ground size ). In the new space there are some things that need to be done, some wishes that should be fulfilled and a lot of construction to do, since we are working with an empty space.
The Great Meeting
Last week, 17 Februari 2016 we had a meeting with some of our members about the new space. We have discussed the minimal requirements for the new space, the nice to haves and the area's we would like to have in the space.
The information about this meeting is available on : [Github]
Planning/Milestones
Current status:
Category | What | When | Who | |
Phase 1 | Preparation | Basic ideas | DONE | Involved |
Contact mezzanine companies | DONE | Davz0rs | ||
Foundation | Contact chosen mezzanine company | DONE | Miep | |
Measure | DONE | External | ||
Place mezzanine | DONE | External | ||
Mezzanine ready | DONE | External | ||
Decide, decide, decide | Make decisions about lighting | DONE | Board with support of participants | |
Spacestate | DONE | Start using WiFi Spacestate button. | ||
Moving of stuff | Move stuff onto mezzanine | DONE | all | |
Main power feed | Install main power feed + switchboard | DONE | High Prio | |
Basic lighting | Add basic lights beneath mezzanine | DONE | Miep | |
Phase 2 | Ground floor | Decide on construction | DONE | External advisor |
Buy materials | DONE | tbd | ||
Build floor | DONE | tbd | ||
Install circuitry in floor | DONE | tbd | ||
Walls | Buy material for walls | DONE | tbd | |
Place ground floor walls | DONE | tbd | ||
Install circuitry in walls | DONE | Miep | ||
Close/finish ground floor walls | DONE | tbd | ||
Create 2nd floor walls/frames | DONE | tbd | ||
Place 2nd floor walls | 80% | tbd | ||
Doors | Build front door | DONE | Miep, Pim | |
Place front door | DONE | miep | ||
Place big door | DONE | miep,tucje | ||
Place locks | DONE | Locks in place | ||
Place doorbell on outside | tbd | tbd | ||
Circuitry | Buy materials | 50% | Miep | |
Network (check for sponsors) | 70% | Miep | ||
Power (check for sponsors) | tbd | tbd | ||
Internet connection | DONE | Miep | ||
Phase 3 | Paint | Decide on paint | tbd | all |
Buy materials | tbd | tbd | ||
Kitchen | Decide on kitchen materials | tbd | tbd | |
Buy kitchen materials | tbd | tbd | ||
Server rack/closet | Build server closet | 80% | tbd | |
Get serverrack from Nifhack | DONE | Miep | ||
Install serverrack | DONE | tbd | ||
Phase 4 | Fuhrniture | Decide on fuhrerniture | DONE | all |
Buy couches | DONE | tbd | ||
Buy stools/chairs | DONE | tbd | ||
Decoration | Decide on art on front | tbd | tbd | |
Paint door/front | tbd | tbd | ||
Steampunk door/front | tbd | sil | ||
Phase 5 | Opening | Decide on date | tbd | tbd |
Invite people/hackerspaces | tbd | tbd | ||
Prepare roadmap | tbd | tbd | ||
Parteh | tbd | tbd |
Drawings
BOM
What we need so far